SR-17 Fuel Break Project Status

Progress Update as of August 22, 2019:

This Week: Final planning continues this week, and the Operations plan for the next two weeks has been approved. Representatives of the project are making contact door-to-door in the community to ask residents for permission to work on private property in the project area.

Week 1 (begins August  26): Crews will begin work in the Redwood Estates Community around the Community Center. Expect minor delays along Madrone Road and the adjacent neighborhood roadways. 

Week 2: Crews will continue and complete any outstanding work around the Redwood Estates Community Center.

Looking Ahead: Updates will continue weekly to keep the community informed of upcoming work areas and impacts.

Close Menu